Plumbing And Drainage System of Hong Kong Airport 3rd Run Way

Project Location: Hong Kong Delivery Time: Sep. 2021 Valves Details: 6 Units SS Penstock 1600X1600, With Bar Screen

Project Details:To Strength Hong Kong's status as an internation aviation hub, and to cater for the city's long-term air traffic demand, Hong Kong International Airport decided to develop into a three-runway system. The scales of the three-runway system ( 3RS ) project is almost equal to building a new airport next to the existing one. 
    
The Plumbing And Drainage System is one of the most important part of the 3rd Run Way. These penstocks are used to collect the rain, isolate the sewage, and prevent the sea water inflow. FRICK finished this job in only 8 weeks, and all the penstocks are properly mounted at site, and passed the final inspection and testing. Now these penstocks are playing important role in Hong Kong Airport 3rd Run Way.

 

1